Ongoing Preconstruction Activities Continue On The New TZ Bridge Project


tzbTappan Zee Constructors, LLC (TZC) will continue preconstruction activities the week of July 8 in Westchester and Rockland Counties.

Ongoing operations:

*Cleaning and preparation for future construction of the Thruway’s Rockland Bulkhead
*Construction of the temporary Westchester work trestle which includes pile driving operations that will occur between 7 a.m. and 7 p.m.
*Survey inspections on existing bridge
*Rockland environmental monitor installations continue
*Geotechnical land borings
*Mobilization at the Exit 10 staging area
*Support for river-based work from the Rockland shoreline

Lane closures will be in place on the right lane of northbound I-87/I-287 on Monday, Tuesday and Friday from 10 a.m. to 3 p.m. for installation of instrumentation to monitor the existing bridge during construction. Lane closures will also be in place on the southbound right lane of I-87/I-287 Wednesday and Thursday from 10 a.m. to 3 p.m. for the same activity.

(Source: MidHudsonNews)