Ramapo, NY: Maple Ave Construction Update


This is an update on the Maple Avenue reconstruction project beginning November 5TH. 

The sidewalk is almost complete from Route 306 to Maple Terrace on the south side of Maple Avenue.

The last piece of drainage equipment will be installed near Maple Terrace on November 5th.

Verizon will be moving their infrastructure from the old poles to the new poles.

The road widening on the south side of Maple Avenue is expected to begin during the week of November 10th.

You will be kept posted as updates occur.

The re-construction project covers the location of Maple Avenue between Monsey Blvd and Saddle River Road. When completed, residents will enjoy a new and wider roadway, new sidewalks, new curbs, bus turning lanes, improved lighting, new traffic lights and improved drainage.

(Dov Gordon – YWN)